East Side Operations and Inspection Plans
Location: City of Troy, City of Rensselaer, RCSD
Status: Project Completed
Date Completed: 12/6/13
West Side Operations, Maintenance and Inspection Plans
Location: City of Albany, City of Cohoes, Village of Green Island, City of Watervliet, Albany County Water Purification District
Status: Project Completed
Date Completed: 12/15/15
Patroon Creek Trunk Sewer Repairs
Location: ACSD
Status: Project Completed
Date Completed: 2011
2011 Storm Sewer Improvements
Location: City of Cohoes
Status: Project Completed
Date Completed: 2011
Washington Avenue Sewer Improvements
Location: City of Rensselaer
Status: Project Completed
Date Completed: 2011
Albany Avenue Green Street Project
Installation of Mechanical Bar Screens
Location: RCSD
Status: Project Completed
Date Completed: 2012
Bouck Tide Gate Installation
Location: City of Albany
Status: Project Completed
Date Completed: 2012
Elberon Place Area Storm Water Storage Phases I and II
Location: City of Albany
Status: Project Completed
Date Completed: 2012
Disinfection Facilities at WWTP (Prior Order on Consent)
Location: RCSD
Status: Project Completed
Date Completed: 2012
Lawnridge / Grove / Glendale / Forrest Avenue Separation Phase II
Location: City of Albany
Status: Project Completed
Date Completed: 2012
Marion Avenue Stormwater Storage Structures
Location: City of Albany
Status: Project Completed
Date Completed: 2012
Woodville Pump Station Upgrades
Location: City of Albany
Status: Project Completed
Date Completed: 2012
Broadway Sewer Separation
Replacement of Mechanical Bar Screens
Location: RCSD
Status: Project Completed
Date Completed: 2012
Sewer Rehabilitation Projects Throughout the City of Albany
Location: City of Albany
Status: Project Completed
Date Completed: 2013
South Plant Disinfection Project
Location: ACSD
Status: Project Completed
Date Completed: 2013
Regulator Capacity Improvements
113th Street Storm Sewer Improvements Plan
113th Street Storm Sewer Improvements Report
Partition Street Trunk Sewer Evaluation
Location: City of Rensselaer
Status: Project Completed
Date Completed: 2014
Asset Management Plans (Troy, Rensselaer, RCSD) (Prior Order on Consent)
Location: RCSD
Status: Project Completed
Date Completed: 2014
Regulator Tide Gate Inspection and Evaluation
Location: RCSD
Status: Project Completed
Date Completed: 2015
Execution of IMA(s) in compliance with Section V(C) of the Order on Consent
Cross Street Sewer Outfall Evaluation
Disinfection Facilities at WWTP (Prior Order on Consent)
Location: RCSD
Status: Project Completed
Date Completed: 5/1/2014
Upper Washington Avenue Groundwater Recharge
Melrose/Winthrop Groundwater Recharge Basins
Location: City of Albany
Status: Project Completed
Date Completed: 6/5/2014
Completion of a Feasibility Assessment for a “Green Infrastructure Banking System”
Development of the Post-Construction Monitoring Program
McCormack Pump Station Upgrades
South Plant Disinfection Project
Location: ACSD
Status: Project Completed
Date Completed: 10/1/2014
Cross Street Trunk Sewer Rehabilitation Phase I
Discharge Notification System for Albany Pool CSOs
Location: Pool-Wide
Status: Project Completed
Date Completed: 11/27/2014
Cross Street Sewer Outfall Repairs and/or Replacement
George Street Sewer Separation
Upgrade Pump Stations Located in Rensselaer
North Swan Street Park Revitalization
Partition Street/Broadway Sewer and Drain Improvements
Upgrade Pump Stations Located in Troy
Regulator Capacity Improvements
Location: City of Troy, City of Rensselaer
Status: Project Completed
Date Completed: 5/21/2016
Performance of a Codes and Local Law Review
Quail Street Green Infrastructure Project
Monument Square Green Infrastructure Project
Route 32 Green Street Project
Swan Street and Hamilton Street Regulator Improvements
Location: Village of Green Island
Status: Project Completed
Date Completed: 4/21/2017
Improvements at up to Eleven Regulators
Mariette Place Stormwater Storage Facility
18th Street and Avenue A Weir Improvements
Green Infrastructure Technical Design Guidance
Improvements at Five Regulators
Middle Vliet Street Sewer Separation
Asset Management Plans (Albany, Cohoes, Watervliet, Green Island)
Location: City of Albany, City of Cohoes, Village of Green Island, City of Watervliet
Status: Project Completed
Date Completed: 12/1/2017
Investigate Non-CSO Bacteria Sources Along Mill Creek, Poesten Kill, and Wynants Kill
Primary Sludge Degritting
Hoosick Street Storm Sewer Extension
Modify Bouck Regulator
Documentation/Reporting of New Public and Private Green Projects
Hudson River Water Quality Public Advisory
Columbia Street Phase II Separation
Beaver Creek Clean River Project (“Big C” Disinfection and Floatables Control Facility)
Mereline Combined Sewage Storage
123rd Street Stream Separation
Implementation of the Post-Construction Monitoring Program
Location: Pool-Wide
Status: Program Underway
Evaluation of Secondary Clarification Improvements
Floatables Control Facility for CSO 026 Outfall (Regulators Maiden, Steuben and Orange) + Floatables Control Facility for CSO 030 Outfall (Regulators Quackenbush, Jackson and Livingston)
Outside Community Metering